Preparations begin for Downtown Revitalization Project
BRANTFORD, ON – The City is pleased to announce that construction for the Downtown Revitalization Project will commence next week. As part of a Council-approved priority, this significant project aims to upgrade both underground and aboveground infrastructure in Downtown Brantford. The enhancements will support future growth, transform downtown into a destination, and improve safety and accessibility for all.
As a first step before the City can begin their planned construction, Enbridge Gas, through their contractor AECON, will begin replacing natural gas infrastructure on Colborne Street, Brant Avenue, Dalhousie Street, and Bridge Street on January 20, 2025.
This essential work is scheduled to take approximately six weeks, weather permitting, and is a critical step in preparing for full construction in the spring.
What to expect
- Replacement of the gas main and individual services to buildings
- Temporary patches on sidewalks following gas line replacement, with permanent reconstruction to take place at a later date
- Temporary lane closures, sidewalk closures, and use of parking spaces during work hours
Work schedule impacts
- Colborne Street (January 20 to 31): Partial sidewalk closure. Pedestrian access will be maintained.
- Brant Avenue (February 3 to 14): Right lane and sidewalk closed. Six parking spaces on Colborne Street East will be occupied.
- Dalhousie Street (February 17 to 21): Right turning lane and sidewalk closed. Vehicles will turn right from the through lane. Six parking spaces on Colborne Street East will be occupied.
- Bridge Street (February 24 to 28): One lane and sidewalk closed. Six parking spaces on Colborne Street East will be occupied.
Supporting local businesses
Sidewalk and business entryway access will remain open wherever possible. Impacted property owners and businesses have been notified directly.
Office hours are held every Tuesday from 6:00 p.m. to 7:00 p.m. for anyone wishing to speak with City staff in person about the project. Appointments can be made outside of these times by emailing cobdowntown@brantford.ca.
Stay informed
The City is committed to working with Enbridge to minimize disruptions and your patience is appreciated as we move forward with this vital infrastructure improvement. Please visit Brantford.ca/NewDowntown to learn more about the Downtown Revitalization Project.
-30-