Inspections
It is the responsibility of the person to whom the permit has been issued to let the Building department know when they are ready for an inspection. A number of inspections are different stages of construction are required by the Ontario Building Code.
To book an inspection, please contact the Building Department at 519-759-4150 or building@brantford.ca at least 48 hours in advance of your desired inspection date. You must provide the Building/Plumbing permit number.
Footing inspection |
When the footings are formed in the excavation and before any concrete is poured. (Where clay area exists, A Type 2 (1 1/2") below grade foam should be installed around perimeter foundation. When the trench/pier holes are excavated for footings and before any concrete is poured. |
Foundation and/or weeping tile |
After foundation has been stripped of formwork and has been damp-proofed and weeping tile is in place and covered with 6" of stone. |
Sewer Rough-In |
When the exterior sanitary and storm sewers have been laid and filled with water and are ready for inspection (prior to backfilling). |
Plumbing Rough-In |
When the plumbing and interior waterlines have been roughed in and filled with water and are ready for inspection. |
Framing Inspection |
When the roof is shingled and the windows are installed, but before any insulation is installed. |
Insulation Inspection |
After insulation and vapour barrier is installed, but before wall finish is installed. |
Pre-Occupancy |
Prior to occupancy of a newly constructed dwelling or addition. |
Completion |
When all work is completed and a Final Inspection has taken place. |